The contractor has completed the excavation work and landscaping required for the various storm drain system repairs between University Hall and the Student's Union building. There is a pathway repair and some line painting (parking lot H & I) remaining, that will be completed prior to the start of classes.
Please obey barricades, signage and detours for your safety and the safety of the workers.