Campus Storm System Repair Project - Update: June 21, 2016
The storm system repairs in Lot J were completed on Saturday, June 18.
McNally Contracting will continue to work in Lot I with an anticipated completion date of July 3. Work includes removal and replacement of existing damaged storm pipe, concrete curb and asphalt.
The next phase will be Lot H, details are forth coming.
Please obey barricades, signage and detours for your safety and the safety of the workers.